US 98 to US 17
Affected Road: Bartow Northern Connector
Capacity Project
From: US 98
To: US 17
FDOT Section #:
FDOT FM or Item #:
Description:
Construct a new two (2) lane road from US 98 to US 17.
Construction Date:
FY 10/11
Road Number:
Bartow Northern Connector
Lanes Added:
2.0
Existing Lanes:
0.0
Total Distance:
6.0
Miscellaneous Information:
30% submitted on 9/24/08;draft Bridge Hydraulics Report received and under review; FDOT is requesting overpass for crossing for trail; 60% plans due 1/6/09; mitigation sites may be available in coordination with NRD.
Program & Status Information:
PDE (YR):
PDE ($):
DSN (YR): FY 09/09
DSN ($):
ROW (YR): FY 09/10
ROW ($):
CST (YR): FY 10/11
CST ($):
Location / Map:
BNC_Revised_Alignment.pdf
Implementing Agency: